Construction Update January 2018
Things are really on the move at Modeina!
Civil construction work is presently under way on Stages 12A, 12C, 14 and 16, which incorporate a total of 100 lots in aggregate. These works are expected to be completed in June 2018, after which work can commence on the expansion of the existing Reserve in Dominion Drive.
The works on Stage 14 include the construction of two new roads – Gates Road and Milano Road – and an extension of Dominion Drive. These new roadways will create access to the future Burnside Primary School within the estate.
It is anticipated that the Victorian School Building Authority will appoint a builder for the school by Christmas. Construction is scheduled to be completed by the end of next year to allow Burnside Primary to open for the beginning of the 2019 school year.
Meanwhile, work on the extension of the Burnside Children’s & Community Centre at Modeina operated by Melton City Council is now under way and the project is expected be completed by the end of 2018.
Council is also expected to be in position to commence the keenly awaited extension of Westwood Drive early in the New Year and complete the connection to the north by late 2018 or early 2019.