Development Updates

Stage 12C

Stage 12C construction commenced September 2017 and it will be complete July 2018

Burnside Primary School

Building works at the site of the new Burnside Primary School are underway and on time for school gates to open on the first day of Term 1, 2019. 

Situated just south of the Burnside Community Centre on Lexington Drive, 
the P-6 school will feature two state-of-the-art learning communities, complete with break-out collaboration spaces, creative activity spaces and withdrawal areas, as well as an administration building with library. 

Spread over 3.5 hectares, the grounds will include a sporting field, two hard courts and open play areas. 
It's expected that enrolment boundaries for the school will be announced by mid year and eligible children will be invited to enrol in Term 3. 
To watch a video of foundations going down at the new facility, go to:

youtube.com/watch?v=eY6MWH68750 

Community Centre

Council will commence construction on the Community Centre expansion prior to Christmas and is due to complete the works in August/September 2018

This will include additional childcare facilities, meeting rooms and an expanded car park.

Westwood Drive

Westwood Drive is due to start construction in the new year and will take approximately 12-14 months to complete. For more information - http://www.melton.vic.gov.au/Council/Major-Projects/Works-Projects/Westwood-Drive-Road-and-Bridge-Construction

Stage 16

Stage 16 construction commenced October 2017 and it will be complete Fourth Quarter 2018.

Stage 14

Stage 14 construction commenced in September 2017 and is due to be completed Fourth Quarter 2018. This stage will also include the road delivery around the new school.

Stage 12A

Stage 12A construction commenced in September 2017 and are now complete.

The second stage of the central reserve will be landscaped and completed by Spring 2018, this will include picnic facilities and a kick about area.

Rockbank Middle Road

Rockbank Middle Road is partly complete and now connects with Lexington Drive giving residents of Modeina and alternative entry / exit to the estate.